1. 1. 2020: Waha Oil 9 GE TM 2500+ Mobile Gas turbine Installation and Adaptation Works: 2 500 000 USD ; ongoing
  2. 2. 2020: TEİAŞ 154kV Ovacık Havza Transformer Center Extension and Rehabilition 2270 550, 00 TL ongoing
  3. 3. 2020: EUAŞ Obruk Hes Protective Relay : 114 000 EURO ; ongoing
  4. 4. 2019: EÜAŞ BİRECİK – NİZİP HES : 420 kV Transformer Center Extension: completed: 3 500 000, 00 TL
  5. 5. 2019 : TEİAŞ 6.BÖLGE MÜDÜRLÜĞÜ : 154 kV UŞAK OSB SUBSTATION : completed; 5 000 0000,00 TL
  6. 6. 2018 : ÇELİKLER HOLDING PAMUKOREN GEOTHERMAL SANTRAL 154kV Substation Construction Works: 450 000 TL ; completed.
  7. 7. 2018 TEİAŞ 12.BÖLGE MÜDÜRLÜĞÜ : Dismantling 37 pieces 154kV and 5 pieces 420 kV disconnecting switch and renewing with motorized switches
  8. 8. 2017 EÜAŞ AMBARLI CCPP 380kV – 154kV Substation Renewing; Primer Equipment Modernisation,Busbar Protection, Renewing complete secondary systems, SCADA systems 2500 000 TL ; completed
  9. 9. 2016 : TURKMENISTAN 110/35/10 kV AKBUGDAY SUBSTATION 2500000 EURO completed
  10. 10. 2016 : TURKMENISTAN 35/10 kV GULMAC 1250 000 EURO ; completed
  11. 11. 2016: TURKMENISTAN 110/35/10kV GARRIKYARIZ substation primary and secondary project design, Protection and SCADA PANELS production : 350 000 US dollars completed
  12. 12. 2016 : TEİAŞ 154/33 kV GONEN SUBSTATION Transformer Protection Panel Renewing and MV Switchgear Modification and new type 5Ş MV Buillding Construction : 1250000 TL completed
  13. 13. 2015: TEİAŞ 154kV DERINKUYU TM 2 Overhead Line Feeder Extension: 1448000TL ; completed
  14. 14. ÇALIK ENERGY TURKMENISTAN AST-1 PROJECT 16 pieces 110/35/10 kV ELECTRICAL PRIMARY AND SECONDARY DESIGN ACCORDING TO SNIP NORMS : 150000 USD ; completed
  15. 15. ÇALIK ENERGY TURKMENISTAN AST-1 PROJECT 4 PIECES 220/110/35/10 kV TRANSFORMER CENTER ELECTRICAL PRIMARY AND SECONDARY DESIGN ACCORDING TO SNIP NORMS ; 50000 EURO completed
  16. 16. YAKINDOST COMPANY 110/35/10 kV 2*25 MVA KAKHA TRANSFORMER CENTER RELAY AND CONTROL PANELS ERECTION , TEST AND COMMISSIONING ; 500000 US dollars completed
  17. 17. TEİAŞ ŞANLIURFA KARACA 154/33 kV TRANSFORMER CENTER 50( 62.5) MVA TRANSFORMER FEEDER ERECTION ; 1565000 TL completed
  18. 18. YEDAS 30 000 MVAR AUTOMATIC CAPACITOR BANK PROJECT; 2650000 TL completed.
  19. 19. AKSARAY ULUKISLA HIGH SPEED RAILWAY ELECTRICAL AND SIGNALISATION PROJECTS design : 100000 EUR completed